Scheduling Functions - Global Changes - Clear Assigned Task Resources

Before using the Global Change function, the schedule should be saved if changes were made manually.

Relevant Icons on Toolbar

Global Changes

Clear Company Contacts or Equipment Resources Assigned to Tasks

  1. In the Gantt Chart listing, select one or more task that have assigned resources which need to be removed by using the circular checkbox on the left.
  2. Click the 'Global Changes' button on the Toolbar.
  3. Check the 'Clear Assigned Resources' option.
  4. Click the blue 'Save' button. This will automatically clear the assigned resources and refresh the Gantt Chart.