Scheduling Functions - Global Changes - Reset Task IDs based on current Sort Order

Before using the Global Change function, the schedule should be saved if changes were made manually.

Relevant Icons on Toolbar

Global Changes

Reset Task IDs based on current Sort Order

  1. Click the 'Global Changes' button on the Toolbar.
  2. Check the 'Reset IDs based on current Sort Order' option.
  3. Click the blue 'Save' button. This will automatically reset the task IDs and refresh the Gantt Chart.